Melato monitors projects

Facebook
X
LinkedIn
WhatsApp
Email
Maluti-a-Phofung executive mayor Malekula Melato at the new Elizabeth Ross substation during an overnight visit.

By Emily Setona

QWAQWA – Maluti-a-Phofung executive mayor Malekula Melato led oversight visits to delayed infrastructure projects in QwaQwa, urging contractors to meet deadlines and EPWP targets amid financial distress, poor performance, and pressure from COGTA and Parliament for accountability.

Melato, accompanied by Members of the Mayoral Committee (MMCs) including MMC for Electricity and Infrastructure Litaba Nhlapho, conducted oversight visits to several infrastructure projects in QwaQwa on Tuesday, 7 October 2025.

The visits form part of the municipality’s renewed effort to fast-track stalled projects and ensure contractors deliver on time, following mounting pressure from the Department of Cooperative Governance and Traditional Affairs (COGTA) and Parliament to improve service delivery in one of the country’s poorest performing municipalities.

The first stop was at the Uniqwa Reversal Water Project, which will store 10 million litres of water to supply Phuthaditjhaba and the Setsing CBD. Project manager Lwazi Msitsini said the project is almost complete, with only waterproofing and leak-testing outstanding. “We are about 96 percent done,” confirmed community liaison officer Lerato Sello from Ward 2 (Clubview).

At the Elizabeth Ross Substation, Mayor Melato and MMC Nhlapho raised concerns about delays. The project team explained that a substation component ordered from China arrived late, causing setbacks. Funding issues were also cited as a contributing factor.

“I hope the project will now run smoothly because when contractors delay, the municipality gets blamed,” said Melato.

“As the mayor, I must report to Parliament on what we are doing, and as one of the lowest-performing municipalities, it’s important that I see progress myself.”

The oversight team also visited the Tseki Welisizwe Rural Bridges Project, which is nearing completion, and the Makwane Road Paving Project, where work has been slower than expected. MMC Nhlapho expressed frustration over the poor performance of some contractors, warning that COGTA has threatened to withhold funding if the municipality fails to complete projects.

“Most of our projects are sitting at six percent progress,” said Nhlapho.

“Contractors will not make us fail. We must deliver because COGTA is monitoring us closely.”Mayor Melato also emphasized that subcontractors must adhere to agreements with the municipality, particularly regarding the hiring of local Expanded Public Works Programme (EPWP) workers.

“When contractors fail to employ the number of EPWP workers we agreed upon, it affects our funding,” she said. “If the target is 100 workers but only 50 are hired, our future allocations are cut.”

The oversight visits come as Maluti-a-Phofung faces scrutiny following damning findings by Parliament’s Portfolio Committee on Cooperative Governance and Traditional Affairs, chaired by Dr Zweli Mkhize.

Earlier this year, Mkhize revealed that the municipality is bankrupt, operating with a deficit of R1.5 billion, and burdened by a R9 billion Eskom debt. The municipality has also received multiple audit disclaimers for poor financial management, irregular expenditure, and failure to collect revenue effectively.

“The situation in Maluti-a-Phofung reflects a deep governance crisis that may take up to 20 years to recover from,” Mkhize said. He also raised concerns about unqualified staff appointments, poor infrastructure maintenance, and allegations of bribery involving councillors.

Melato’s oversight tour highlighted the urgent need to restore accountability, improve project management, and ensure that community members benefit from ongoing developments.

“We cannot afford to continue failing our people,” Melato said.

“We are committed to completing every project and rebuilding confidence in this municipality.”

As Maluti-a-Phofung battles debt, infrastructure decay, and funding threats, the success of these projects may prove critical to turning the tide in one of the Free State’s most troubled municipalities.

Leave a Reply

Your email address will not be published. Required fields are marked *

Bloemfontein
10/11
Mon
15°C
overcast clouds
Tue
daily_wether_icon
23°C
26°C
Wed
daily_wether_icon
27°C
31°C
Thu
daily_wether_icon
30°C
31°C
Fri
daily_wether_icon
29°C
19°C
Sat
daily_wether_icon
17°C
18°C
Sun
daily_wether_icon
23°C
19°C
Mon
daily_wether_icon
21°C
21°C
Related Posts
IMG-20251106-WA0006
Read More
Murder accused Tshepang Mapiloko.
Read More
IMG-20251014-WA0034
Read More
29 October 2025
FS spends R2bn on road maintenance
By Teboho Moloi VILJOENSKROON – The Free State Department of Community Safety, Roads and Transport has...
27 October 2025
Mokoena hands over R2.5 million to boost water quality monitoring in Thabo Mofutsanyana
By Emily Setona KESTELL – The Free State MEC for Cooperative Governance, Traditional Affairs and Human...
23 October 2025
Councillors raise alarm over service delivery delays in MAP
By Emily Setona QWAQWA – Concerns over poor service delivery took centre stage during the Maluti-a-Phofung...
23 October 2025
Bridgette Lebesa honoured by SALGA
By Emily Setona QWAQWA – Maluti-a-Phofung Municipality’s Member of Mayoral Committee (MMC) for Sports,...
23 October 2025
Councillors demand action, not excuses- Dlamini
Maluti-a-Phofung council speaker Mandlenkosi Dlamini stating that councillors want action from the Executive...
09 October 2025
Melato monitors projects
By Emily Setona QWAQWA – Maluti-a-Phofung executive mayor Malekula Melato led oversight visits to delayed...
08 October 2025
Youth movement plots Kestell comeback
By Teboho Moloi KESTELL – Frustrated by years of economic decline and high unemployment, a group of determined...
03 October 2025
Maluti-A-Phofung ‘trying’ amid mounting service delivery failures
By Teboho Moloi QWAQWA – The Maluti-A-Phofung (MAP) Local Municipality says it is “trying” to improve...
01 October 2025
Basebetsi ba projeke MAP ba re ba lebetswe
Ka Teboho Moloi QWAQWA – Basebetsi ba projeke ya ho hokelw a ha marangrang a tsamaisang dikgwerekgwere...
30 September 2025
R64m disaster funds unused by FS municipalities
By Teboho Moloi BLOEMFONTEIN – Six Free State municipalities have failed to spend a combined R64 million...